10 |
Fiddlers Elbow, Quakers Yard |
Repair of damaged trash screen on lnlet to culvert under Fiddlers Elbow roundabout. |
Work is expected to start in Autumn 2020 |
14 |
Mill Road, Quakers Yard |
Removal of fallen trees and stabilisation of highway embankment caused by river erosion. |
Work started in August 2020 |
23 |
Victoria Bridge, Quakers Yard |
Masonry repairs to damaged east abutment with scour protection. |
Work is expected to start in early 2021 |
26 |
Edwardsville Cemetery |
Replace and upsize 80m section of undersized culvert from Beechgrove Cemetery to Forest Grove. |
Work is expected to start in 2022 |
27 |
Pentwyn Deintir, Quakers Yard |
Replace and upsize section of culvert under Pentwyn Deintir with new headwall. |
Work is expected to start in 2022 |
36 |
Rock Houses, Quakers Yard |
Reinstate embankment with scour protection. |
Work is expected to start in spring 2021 |
42 |
Woodland Park, Quakers Yard |
Reinstate embankment with scour protection. |
Work is expected to start in spring 2021 |
46 |
Taff Bargoed Park |
Scour protection to washout in cascade. |
Work has been completed |