Ar-lein, Mae'n arbed amser
Cofnod Datgeliadau
Cofnod Datgeliadau Chwilio
Defnyddiwch y rhan hon o'r safle ar gyfer hidlo'r canlyniadau chwilio foi.
Defnyddiwch y rhan hon o'r wefan i weld Bas Data cofnod datgeliadau'r Awdurdod.
Cofnod Cyf : EIR 2288
Dyddiad Dderbyniwyd : 05/06/2025
Dyddiad Cwblhau : 30/06/2025
Sefydliad : Coal Action
Math y Cais : Company
Categori : Planning Applications
Cwestiwn
In the Tactical Working Group meeting notes for 24th March 2025 obtained under EIR, MTCBC is noted as saying in relation to P/25/0037:
"MTCBC advised that around 230 representations have been made to date, with the vast majority from Friends of the Earth and Coal Action Network. This commentary is objecting as the application would not be implementing the previously approved scheme. The vast majority of these representations are from individuals who are not residents of Merthyr, so UK-wide representation is being made."
I would like a copy of the records that led MTCBC to tell parties present at this meeting both these points:
1) the vast majority of representations were from Friends of the Earth and Coal Action Network
2) that the majority of these representations are from individuals who are not residents of Merthyr
Records can be summary and redacted to comply with GDPR - but time taken to do that should not be factored into the cost-cap associated with FOI requests. Note that if it is considered that the cost cap is still engaged by this request, please fulfil it to the extent possible whilst remaining within the cap and provide a detailed breakdown for how the request exceeds the cost cap in full. Refusal will be robustly challenged.
Previously attached doc:
FINAL
Ffos-y-Fran Technical Working Group Meeting Notes
24 March
Welsh Government Offices, Merthyr Tydfil
Attendees
– Welsh Government
– Welsh Government
– Welsh Government
– Welsh Government
– Merthyr Tydfil CBC
– Merthyr Tydfil CBC
– Merthyr Tydfil CBC
– Merthyr Tydfil CBC
– Merthyr Tydfil CBC
–Merthyr Tydfil CBC
– Natural Resources Wales
– Natural Resources Wales
– Natural Resources Wales
– Mining Remediation Authority
– Mining Remediation Authority
– HSE
1. Section 73 application for revised restoration scheme
Since receipt in February, the application remains under consideration by MTCBC.
A fact finding/site visit arranged for the Technical Working Group has been arranged
for the 7 April at Cwmbargoed disposal point to discuss application. There is
currently minimum plant on site, and a plant supplier has already contacted MRA
regarding any potential future Ffos Y Fran needs – officials raised concerns
regarding whether on-site plant would meet the needs of a restoration scheme.
The application is currently going through the consultation exercise. Council highway
engineers have not raised any initial concerns, and ecologists are looking for
background information for the ecological impact assessment.
FINAL
MTCBC advised that around 230 representations have been made to date, with the
vast majority from Friends of the Earth and Coal Action Network. This commentary is
objecting as the application would not be implementing the previously approved
scheme. The vast majority of these representations are from individuals who are not
residents of Merthyr, so UK-wide representation is being made.
Concerns were raised by attendees regarding the general detail within the
application and lack of supporting evidence, with the following specifics raised:
• Detail lacking on pumping proposals to temporarily lower the water level in the
flooded excavation to facilitate earth working operations (re-grading the low
wall backfill batter)
o Pumping volumes and rates
o Discharge points and necessary consents
o Seasonal constraints
• Absence of site drainage arrangements within proposal
• Costings have not been included with the application or provided to Merthyr
separately
• How the revised restoration proposals tie-in with current Phase 2A works and
proposals for future Phase 2B
• Application is lacking proposals for the many attenuation ponds and lakes
across the site
• Aftercare - Care and maintenance-post restoration. What plans are in place
and for how long, and who is responsible?
A Community liaison meeting will take place on the evening of 7 April.
MTCBC has commissioned a geotechnical expert to review the application.
2. Phase 2A
While the operator stopped most restoration works in early December due to
inclement weather, machinery is moving once more with reprofiling, topsoil and
seeding work taking place. A significant amount of machinery either has been or is
being sold, with only "adequate" machinery left on site for restoration.
Works on Area 8 (eastern side) have not been agreed due to concerns from the
MTCBC ecologist.
3. Phase 2B works proposals
Initial discussions between the Operator and MTCBC on Phase 2B have begun, with
the Operator looking at areas that can be restored in line with the agreed restoration
scheme. An area adjacent to the A4060 trunk road is being considered for profiling
works, and most additional works would take place towards Bogey Road on the west
flank of the void.
The Operator has suggested tidying areas around buildings and works to the high
wall where the viewing platform is situated.
FINAL
MTCBC and the Operator are looking for a steer on drainage works in restored
areas. There are currently unlined ditches in place directing water into the void but
the Operator is looking at formalising these channels and how best to line them. The
Operator originally suggested concrete canvas, MTCBC raised some initial concerns
and suggested stone lining in some areas would be preferable.
Drainage is currently not included in the application, and it is unlikely for formalised
drainage works to be seen this year. The drainage scheme under the currently
approved strategy is viewed as not fit for purpose and requires further development
(defining catchment areas, ditch routes, ditch linings, discharge points etc.),
however, temporary drainage can be put in place. NRW noted that any drainage
must align with NRW permits.
Phases 2A and 2B could be running concurrently dependent on agreements.
Concerns were raised by attendees that the Operator has demonstrated an apparent
unwillingness to include higher priority restoration works within either Phase 2A or
proposals for Phase 2B.
MTCBC advised that a more detail draft of the programme of works for phase 2B
should be shared following Easter.
No agreement has been reached to allow Phase 2B work to commence. This is still
work in progress with MTCBC and the Operator reviewing scope, programme and
costs.
4. Call-in Request
WG confirmed that a request is being considered to call in the Section 73 application
for determination by the Welsh Ministers. The call-in request is under active
consideration although MTCBC (and the Carmarthenshire Joint Minerals and Waste
Unit, which is advising MTCBC on the application) should continue to process the
application as normal.
5. MotoCross Application
An EIA screening exercise for a planning application for a MotoCross track on tip
OB3 has been completed. The proposal is focused on the plateau itself and with no
consideration for retention of the sides. The application would be contingent upon
site restoration.
6. AOB
A watercourse survey has been unable to progress on the site despite having been
commissioned by MTCBC. This is principally due to their being a lack of information
available to inform assessments.
MRA stated that any highwall trimming had the potential to encounter/disturb insitu
coal seams which would require agreement from the MRA prior to works. From
FINAL
discussions with the Operator, MTCBC do not believe that coal would be excavated
as part of the revised restoration scheme where ‘over digging’ was required but are
mindful that of this possibility.
The current water level was report as 279m AOD.
7. Next Meeting
TWG to attend site visit with operator on 7 April.
Action 1 – WG and MTCBC to arrange meeting between lawyers
Ateb
In the Tactical Working Group meeting notes for 24th March 2025 obtained under EIR, MTCBC is noted as saying in relation to P/25/0037:
"MTCBC advised that around 230 representations have been made to date, with the vast majority from Friends of the Earth and Coal Action Network. This commentary is objecting as the application would not be implementing the previously approved scheme. The vast majority of these representations are from individuals who are not residents of Merthyr, so UK-wide representation is being made."
I would like a copy of the records that led MTCBC to tell parties present at this meeting both these points:
1) the vast majority of representations were from Friends of the Earth and Coal Action Network
2) that the majority of these representations are from individuals who are not residents of Merthyr
As a matter of normal practise, we do not provide copies of the representations received. Upon request the representations can be inspected in person at our offices and sufficient time would need to be given in order that any personal information can be appropriately redacted.
In response to the two points raised, at the time of the technical working group meeting in March 2025, the vast majority of the representations received appeared to have been received through the Coal Action Network website, which in most cases included reference to an ‘actionnetwork.org’ email address. Some representations included personal emails, but followed the same format. The majority of these representations do not provide a postal address but instead largely indicate that they are from England or other distant locations outside of Merthyr Tydfil. As such, they did not appear to be representations from local residents. We are aware that both Coal Action Network and Friends of the Earth are active campaigners for the restoration of the site, hence the reference to these groups. Since the above mentioned meeting, further representations have been received from Friends of the Earth which includes a petition with a mixture of signatures from residents of Merthyr Tydfil and from neighbouring towns/areas.